NextGen Student Deployment Timeline
The following timeline indicates when each functional area group will be in the different stages of the NextGen Student project. View the timeline as an image.
Workday feature releases: Every September and March.
Significant milestones: October and December of 2028. March, May, July, and September of 2029.
| Stage | Academic Foundation | Recruiting and Admissions | Records and Advising | Financial Aid | Student Financials | Student Worker |
|---|---|---|---|---|---|---|
| Customer Prep | December 2024 - April 2025 | December 2024 -April 2025 | December 2024 - April 2025 | December 2024 - April 2025 | December 2024 - April 2025 | April 2025 |
| Plan | May 2025 - February 2026 | May 2025 - February 2026 | May 2025 - February 2026 | May 2025 - February 2026 | May 2025 - February 2026 | May 2025 |
| Architect and Configure Workset A | March - September 2026 | March - September 2026 | March - September 2026 | March - September 2026 | March - September 2026 | May - September 2026 |
| Architect and Configure Workset B | October 2026 - February 2027 | October 2026 - February 2027 | October 2026 -February 2027 | October 2026 -February 2027 | October 2026 -February 2027 | N/A |
| Architect and Configure Workset C | March - July 2027 | March - July 2027 | March - July 2027 | March - July 2027 | March - July 2027 | N/A |
| Architect and Configure Workset D | N/A | N/A | August 2027 - January 2028 | August 2027 - January 2028 | August 2027 - January 2028 | January 2028 |
| Test | August 2027 - August 2028 | August 2027 - November 2028 | February 2028 - August 2029 | February 2028 - August 2029 | February 2028 - August 2029 | February - November 2028 |
| Deploy MTP1 | September 2028 | September 2028 | September 2028 | September 2028 | September 2028 | September 2028 |
| Deploy MTP2 | N/A | N/A | February 2029 | February 2029 | February 2029 | February 2029 |
| Post-Production Support and Hypercare | October - December 2028 | December 2028 - February 2029 | March - November 2029 | March - November 2029 | March - November 2029 | March - September 2029 |
| Extended Care | January 2029-May 2030 | March 2029 - May 2030 | September 2029 - May 2030 | September 2029 - May 2030 | September 2029 - May 2030 | N/A |